Syrena Hotels; METROPOL HOTEL, Warsaw, Poland: Recommissioning of Existing Smoke Control System and Commissioning of New Design and Installation
- Recommissioning of Existing Smoke Pressurization As Built Documents, Installations and Automatic Controls dated February 2004.
- Technical Report with Recommendations for new Smoke Control System for Lifts Shaft Pressurization in accordance with NFPA 92A Standard for Smoke-Control Systems and BS EN-12101-6 Norm.
- Prepared Concept Design, Budget Cost for Design and Construction Works.
- Commissioning of Tender Design.
- Prepared Tender Documents and Managed Tendering
- Commissioning of Execution Design.
- Commissioning of New Works.
- Managed Handover of works to the Owner.
Construction area: 15 000 m2
Completion Date: October 2013